Kaskus

Hobby

bombiAvatar border
TS
bombi
Ocean Engineering
OCEAN ENGINEERING

Profile:
•\tAn education institution improved offshore technology basically on ocean infrastructure and offshore environment

Competencies:
•\tOffshore engineering technology
With specialization in offshore infrastructures for oil and gas production and exploration
•\tCoastal engineering technology
With specialization in coastal protection technology, port and harbor development, dredging and reclamation
•\tUnderwater acoustic technology
With specialization in underwater acoustic for underwater survey and mapping
•\tOffshore environmental management
With specialization in offshore environmental management for oil spill, sedimentation and scouring

That what we did:
•\tOffshore engineering infrastructures
Spoiler for offshore engineering infrastructure:

•\tCoastal engineering technology
Spoiler for coastal engineering technology:

•\tUnderwater acoustic technology
Spoiler for underwater acoustic technology:

•\tOffshore environmental management
Spoiler for offshore environmental management:


Prospects:
•\tEPC Company: J.Ray McDermott, SAIPEM ENI, Technip, Nisconi, Amec Berca, Drydock World, Aker Solution, FMC, Keppel FELS, etc
•\tEngineering Consultant: Worley Parson, INTEC Engineering, JP Kenny, Genesis Engineering, JGC, KBR, 2H Offshore, etc
•\tOil and Gas Company: Chevron, BP, Total E&P, Pertamina Hulu Energi, Hess, Star Energy, Premier Oil, Conoco Philips, Exxonmobil, etc
•\tConstruction/installation Company: Subsea7, Acergy, Heerema Marine Contractor, etc
•\tNational Company: Perusahaan Gas Negara, PPGL, Bappeda, Badan Riset Kelautan dan Perikanan, Pelindo, BP MIGAS, etc
•\tCoastal Engineering Consultant: East Marine, Penta-ocean, etc

Just for share emoticon-I Love Indonesiaemoticon-I Love Indonesia

Lecture:
Spoiler for Lecture:


News Highlight !
Spoiler for Teknik Elektro dan Teknik Kelautan ITB Raih Akreditasi ABET Pertama di Indonesia:
tata604Avatar border
tata604 memberi reputasi
1
39K
321
GuestAvatar border
Komentar yang asik ya
Mari bergabung, dapatkan informasi dan teman baru!
Teknik
Teknik
KASKUS Official
3KThread1.2KAnggota
Tampilkan semua post
bombiAvatar border
TS
bombi
#103
Lecture 5: Offshore Fixed Platform Project & Design Phase
Offshore Fixed Platform Project & Design Phase

In oil and gas industry, there are some significant different between civil infrastructure and oil and gas infrastructure. Typically, in oil and gas, it consists of several project phases which are:
Phase 1 : Appraisal, to develop Plan of Development (POD) after exploration activities (drilling and geophysical surveying)
Phase 2 : Front End Engineering Design (FEED) or Concept Selection.
In this phase, Company will involve following steps in all disciplines of project such as process, mechanical, electrical, instrumentation in addition to structural engineering. Sometime, it is known as preliminary design. During this phase, Company will perform several activities as follows:
- Collection process data and identifying needs and equipment.
- Preliminary equipment sizing and area requirements
- Weight estimation based on past projects
- Identification of structural configurations
- Preliminary estimation of structural weight
- Identification of installation methods
The data collected during FEED will be further verified to make sure the authenticity and reliability of such data for further use. A Design Basis will be developed for the proposed facility.
Phase 3 : Engineering, Procurement and Construction (EPC). D
etailed design of offshore platform will be initiated once the basic design confirms the economic viability and technical feasibility. In the detailed design/engineering of an offshore platform following items of the jacket and deck will be developed in detail, such as: framing plans, framing elevations, joint details, plate girder details, pile make-up, appurtenances, etc.
The following detailed design analysis as minimum should be carried out:
- Inplace
- Loadout
- Sea transportation
- Lifting
- Free floatation
- Upending
- Dynamic
- Fatigue
- On Bottom Stability
- Pile Driveability
- Ship Impact
Pre-commisioning and commisioning will commence once the facility are installed at offshore prior to hand over to the Company.
Phase 4 : Operation.
In this phase, all activities are taken care by Company.
Phase 5 : Abandon.
The entire facilities should be abandoned once the field has not sufficient to produce much hydrocarbon and the service life of the facilities are ended.